Surrey Hydrodemolition Case Study
AmmLee Group International was tasked with carrying out Robotic Hydrodemolition to the beam to full depth up to the face of the Column/intersecting beam the total area to be removed was 9m³. Time to complete was 8 days.
Challenge
Carrying out the hydrodemolition safely and HAVS free.
Solution
Robotic Hydro demolition using the Falch Multi worker at 2500 bar 22lpm
Result
The project was completed a day early and to the clients satisfaction.
Project details
Client: NDA
Services provided: Robotic Hydrodemolition
Location: Epsom Surrey, United Kingdom
Timeframe: 8 days